Home » Service & Support » Technical Documentation
SAMSON Positioners - Commissioning Procedure
Release time:2026-11-22 09:38:23 | Views:

Commissioning of SAMSON positioners (Mounting and Start-up) follows the sequence of mechanics and pneumatics first, electrics second, parameters and initialization last. The 3730 / 3731 series are operated locally via a single rotary pushbutton and LCD; the INIT key starts autotune, and configuration can also be done with TROVIS-VIEW and a HART communicator. This article covers pre-commissioning checks, mounting and wiring, parameter setting, initialization and common error codes.

I. Scope and Tools

ItemDescription
Applicable seriesSAMSON 3730-0/1/2/3/4/5/6 and 3731-3/3731-5 (the 3730-6 additionally includes pressure monitoring)
Local operationSingle rotary pushbutton (turn to select, push to confirm); LCD reading direction rotatable by 180 degrees
AutotuneINIT key starts initialization; closed-loop operation begins immediately afterwards
Software toolTROVIS-VIEW via SSP interface (RS-232 / USB)
Communication toolHART communicator / FSK modem (HART models only)
Reference documentsSAMSON model-specific mounting and start-up manuals, NA 0122, T 8384-x / T 8387-x

Before commissioning, confirm that the model, data sheet and certificates are available and check the site area classification and intrinsic safety / flameproof requirements.

Source: SAMSON official data sheets NA 0122, T 8384-3/6 EN, T 8387-3 EN and the corresponding mounting and start-up manuals.

SAMSON 3730 series intelligent electro-pneumatic positioner
SAMSON 3730 series positioner, same-series illustration; for illustration only, not the actual model; parameters subject to the official data sheet

II. Pre-Commissioning Checks

Check itemRequirement
NameplateVerify model, spring range and fail-safe action FA (stem extends / air-to-open) or FE (stem retracts / air-to-close)
Air qualityISO 8573-1: particles class 4 / oil class 3 / humidity class 3; flush pipework, oil-free and dust-free
Supply pressure1.4-7.0 bar (3731-323: 1.4-6 bar); air-to-open supply approximately spring range upper limit plus 0.2 bar, minimum 1.4 bar
Mounting interfaceBracket and shaft match integrated Type 3277 / NAMUR IEC 60534-6-1 / VDI/VDE 3845 and 3847
Feedback rodConnecting pin in the correct hole for travel / angle (commonly 25 / 35 / 50 / 90 degrees)
Electrical conditionsCurrent source only; static destruction limit plus/minus 33 V; minimum current approx. 3.6-3.8 mA
Ex integrityHousing, seals, glands, blanking plugs and grounding intact; certificate matches area classification

Low air supply, loose mounting or a reversed feedback rod are common causes of initialization failure; eliminate them before starting INIT.

Source: SAMSON official mounting and start-up manuals (connections / air supply / electrical connections), data sheets T 8384-3 EN and T 8387-3 EN.

III. Mechanical and Pneumatic Mounting Steps

StepAction
1Remove protective caps from pneumatic connections; verify connecting plate / gauge block ports (1/4 NPT or G 1/4)
2Mount the positioner on the valve / actuator and connect signal pressure per FA, FE and NAMUR or VDI/VDE 3845
3Connect supply air; keep tubing short to avoid signal delay; fit SUPPLY / OUTPUT pressure gauges where practical
4Set the Air-to-open / Air-to-close slide switch so that valve closed corresponds to the 0% reading
5Rough-set supply pressure from the nameplate spring range and verify full stroke movement without sticking
6Only then connect the electrical signal (next section) and proceed to start-up settings

Double-acting actuators require the Type 3710 reversing amplifier; rotary actuators follow the actuator manufacturer's pneumatic specifications.

Source: SAMSON official mounting and start-up manuals (pneumatic connections and start-up sequence); data sheet T 8387-3 EN.

IV. Electrical Connections and Ex Requirements

ItemRequirement
Signal sourceCurrent source only (4-20 mA); never connect a voltage source directly; set point wires to terminals 11 and 12
Cable / terminalsM20x1.5 gland clamps 6-12 mm; terminals 0.2-1.5 mm² (3731: 0.2-2.5 mm², at least 0.5 Nm)
IS loopPer EN 60079-14 clause 12; clause 12.2.2.7 for multiple IS circuits in multicore cable; insulation radial thickness at least 0.2 mm and single-wire diameter at least 0.1 mm
Parameter matchingWhen interconnecting, do not exceed certificate values Ui/Ii/Pi/Ci/Li (versus barrier Uo/Io/Po/Co/Lo)
Ex nA / Ex tcZone 2 equipment: connect or disconnect under power generally only during installation, maintenance or repair; associated fuses outside the hazardous area
Ex d (3731)Certified entries / conduit; certified plugs for unused entries; equipotential bonding; never open while energized
Signal faultsAbove 22 mA shows OVERLOAD; below 3.7 mA moves to SAFE and shows LOW

Ex ia intrinsic safety is not Ex d flameproof enclosure: wiring and cover-opening rules differ. Follow the nameplate and certificate on site; where unavailable, write "please consult for confirmation".

Source: SAMSON official mounting and start-up manuals (electrical connections), data sheets T 8384-3/6 EN and T 8387-3 EN; EN 60079-14 and EN 60079-1.

V. Parameterization, Initialization and Error Codes

Code / stepMeaning and action
P2ATO / ATC: air-to-open (fail-close) or air-to-close (fail-open); must match the slide switch
P3Feedback rod pin position: 25 / 35 / 50 / 90 degrees
P4Rated travel range; P5 characteristic (linear / equal percentage / reverse equal percentage)
P6 / P7Input signal (4-20 mA, split range possible); w/x action direction (direct / reverse)
P8Gain Kp (set during initialization; reduce and re-initialize if oscillating)
P9Output pressure limit (approx. 2.4 bar to protect the actuator)
P15Start initialization (INIT); press * during the process to interrupt and return to fail-safe
P16Zero-point calibration (execute when E0 appears)
P18 / P19Reset to defaults / confirm configuration (auto-cancels after 3 minutes without key action)
Error codeCommon cause and action
E0Zero drift above approx. 5%: check mounting and seat, run P16 zero calibration
E1 / E2Parameter changed after initialization / not initialized: restore parameter or run P15
E3Oscillation from excessive Kp: check output air volume, reduce P8 and re-initialize
E4 / E5Actuation time too short / no detection: check air supply, mounting and volume settings
E6 / E7Travel not reached / actuator not moving: check supply, leakage and signal below 3.7 mA
E8Position signal out of limits: check pin position, feedback rod and NAMUR connection orientation
E9 / E10-E15Internal software / hardware fault: return to SAMSON for repair

Source: SAMSON positioner mounting and start-up manual code tables (P0-P20, E0-E15); data sheets T 8384-3/6 EN and T 8387-3 EN.

VI. Selection Guide and Common Models

Selection guide: The commissioning path is mechanics and pneumatics, then electrics, then parameters, then INIT, then verification and records. First verify FA/FE and spring range from the nameplate, ensure air quality and supply, then connect the current source and check Ex wiring. Parameters P2 (ATO/ATC), P3 (pin position), P4 (travel) and P5 (characteristic) must match the site, followed by P15 initialization. On failure, troubleshoot via E0-E15 rather than repeating INIT blindly.

Common models: Applies to the 3730-0/1/2/3/4/5/6 and 3731-3/3731-5; the 3730-6 TS safety version additionally follows the SIL certificate (968/V 1161) and the 3.8 / 4.4 mA emergency shutdown thresholds.

If you encounter E0-E8 initialization errors during site commissioning, or are unsure whether ATO/ATC and intrinsic safety wiring comply with the certificate, please feel free to contact us. We can review the steps and fault causes against the nameplate, air supply conditions and area certification.

Orders & Inquiries

Baoman Industrial Technology (Chengdu) Co., Ltd
Tel: +86 028-60220547 | Email: info@bit-cd.com
Address: Room 1108, Building A, Tingbiao Central Plaza, No. 158 Erxianqiao East Road, Chenghua District, Chengdu, Sichuan Province, China

The information above is not guaranteed to remain valid at all times. Subsequent changes will not be notified separately. Please confirm the latest information at the time of inquiry.